The model, with the hood up.

A monthly, three-phase development model (model.py, reproducible) that a three-person red team took apart and rebuilt. Pick a scenario. Every number on this page is a projection, not a forecast.

Scenario explorer

Founder cash flow by year

Revenue, gain and guaranteed debt

What moves the answer

One change at a time from the go case (1.66x founder multiple, pre-tax). Hard cost dominates; deposit treatment and partner terms are next.

From 5.4x to honest

The first draft claimed 5.4x. It rested on several generous assumptions at once. Each bar adds one dose of realism, cumulatively, in the same monthly engine. The first bar approximates the draft's inputs, so it does not exactly reproduce 5.44x.

  • Realistic entitlement (18 months to a lease, 9 to the presale gate)
  • Buyer deposits held in escrow, not spent on construction
  • Market capital stack: 65% LTC, 10% founder cash, 10% pref + 30% promote
  • Bottom-up cost, dues, cap rate and dead-pursuit costs

Key assumptions

Kill gates

If any gate fails, the default is to stop, not to look for a reason to proceed.

GateThresholdWhy
Counsel opinionIn writing before any pre-development spendDeposit and hard-contract timing decide the capital stack
Closed-comp pricingBlended ≥ $230/sf at the target airportAt $218/sf the plan returns ~1.0x
GMPHard ≤ $125/sf, all-in ≤ $170/sf, from two GC budgets$135 hard returns 1.26x; $145 returns <1x
SponsorApproved ALP + NEPA, sponsor-funded taxilane and stubs, ≥ 40-yr term, ≤ $0.60/sf/yrTimeline and cost
Demand≥ 40 type-qualified owners within 30 min; ≥ 16 refundable reservations in 60 days~2x coverage for 12+ hard presales
RentalsNo comparable box-hangar rentals at the fieldOtherwise buy-vs-rent defeats the price
Lender≥ 65% LTC at ≤ 60% presales with a bonded GMPCapital stack
Pre-developmentStop at $225k without a signed ground leaseCap on dead money

Run a single phase yourself.

The prototype's pro forma lets you move land rate, hard and soft cost, presales, prices, interest and retained units, with a live loan-unlock meter and sensitivity grid.

Open the phase pro forma