From a list at the FBO to a key on your ring.
A Hangar Row phase is 20 units on one taxilane. Here is what happens, in what order, who does it, and where your money sits at each step. Timings are the plan's P50 projections.
The phase timeline
Click a milestone. Month 1 is the first month after the go decision.
Projection. The entitlement period to an executed ground lease is a P50 of 18 months (P25 ~12, P75 ~26). One Henderson complex took about four years of planning (AIN).
One building, three packages
Every unit uses the same pre-engineered steel frame and fire-rated separation walls. Packages are locked at hard contract and built in pre-engineered, pre-permitted positions. No changes after the builder's buyout date.
Schematic section, not to scale. Positions are illustrative.
Where your deposit sits
The plan's base case holds every buyer deposit with an independent escrow agent until closing. Releasing deposits into construction is treated as an upside case that needs a written counsel opinion first.
Arizona
Units zoned and restricted to commercial or industrial use may be exempt from public-report rules (A.R.S. 32-2181.02(B)(1)). If not, pre-report reservations are capped at refundable deposits of ≤ $5,000. Statute · ADRE form
Nevada
NRS 116.411 requires deposits to be escrowed or bonded, but NRS 116.12075 says the chapter generally does not apply to nonresidential condominiums unless the declaration opts in. 116.411 · 116.12075
Utah
Condominium Ownership Act (Utah Code Title 57, Ch. 8). Not yet reviewed. Counsel must answer the same three questions for every state before any presale.
Factual summary of the plan's legal checklist. Not legal advice.
What you own after closing
The unit
A leasehold condominium unit with 40-50 years remaining on the ground lease, extension options tied to capital improvements, and leasehold-mortgagee protections.
The association
Run by a third-party manager: taxilane, apron, master insurance, reserves and the ground-rent pass-through. About $533/month (estimate). The board turns over to owners at the earliest statutory point.
The rules
The condo documents pass down the FAA's 2016 policy on non-aeronautical hangar use (81 FR 38906). Aircraft first.
The paperwork
A "Will my plane fit?" sheet with your aircraft drawn to scale, a buy-versus-rent page, warranties assigned through from the builder and door maker, and an ownership checklist.
See a phase in the prototype.
Click a unit, configure a package, check your airplane against the door, and walk through a sample reservation.